1. When the flooring
is to be installed directly on concrete, a PE film must first
cover the subfloor (6 - 8 mil /0.2 mm vapor barrier), prior to
installing PE foam (3/32- 2.4 mm). Overlap PE film by 8/20
cm and tape the seams. Allow PE film to rise +/- 2/5 cm up
the walls. Lay foam in the same direction as the floor. Do not
overlap. When starting the installation, it is best to begin in
a corner. Lay the first panel with the groove towards the wall.
Set the distance to the wall (5/16/8 mm) using the laminate
flooring spacers. Then fit the first 3 rows of panels without
gluing. |
 |
 |
2. For accurate
cutting of the last panel, rotate through 180 degrees and (with
the pattern upwards) place beside the already existing row, so
that tongue lies over tongue. Include the 5/16/8 mm in play
at the end. When using hand saw, always saw from the upper
surface of the panel in order to avoid splintering the edges.
When using an electric jig saw or a hand-held circular saw the
patterned side must be placed facing downwards. |
 |
3. Important:
The panels must follow the line of the wall. If the wall is not
straight, then the line of the wall must be marked on the first
(still unglued) panel row using a spacer. Either saw the panels
longitudinally according to the marking or use the tapered
spacers to ensure squareness. |
 |
4. Check that the
first row is straight using the guideline. Start each new row
with the leftover piece from the previous row. However, the end
of each panel row should be staggered by at least 16/40 cm
from the previous row. If not, shorten the first panel. This way
you will ensure the best appearance. |
 |
5. Gluing the panels.
The adhesive is to be applied to the top of the tongue of the
panel on the floor (as per the sketch), both lengthwise and
crosswise. Also apply adhesive to the bottom of the groove of
the panel being installed, both lengthwise and crosswise. Allow
excess adhesive a slight drying period (+/-15 minutes), then
remove with a plastic spatula. Clean remaining adhesive film
with a damp cloth. Cloth should be rinsed frequently. |
 |
6. Now panel to panel:
carefully but firmly join the panels completely with hammer and
tapping block. Once the seams are clean and tight, it is
recommended to tape the seam with a good quality tape (i.e.
2/ 5 cm ) to avoid plank movement. Warning: do not damage the
tongue side of the panel. Ensure that the tongue of the panel is
seated in the groove of the Laminate Flooring tapping block! |
 |
7. Ensure that the first two rows are laid exactly straight.
A chalk line or straightedge will help to verify this.
Note: It is imperative to stagger the end seams to ensure a
solid floor construction and maximize appearance. |
 |
8. And now row after
row: Always place the first panels of a row together without
gluing, fit together, saw to size - and then glue. Always use
the specially designed pull-bar for the last panel.
Note: An alternate panel tightening technique is the patented
Quick-Fit system. Simply attach suction cups on alternating
panels and tighten straps using the lever-action device. |
 |
9. Where heating pipes
or room dividers, for example, protrude from the floor, first
cut the panel to the correct length, then lay the panel beside
the actual position, measure the recesses with a ruler and drawt
in. |
 |
10. Now drill out the
marked sections: remember the 5/16/ 8mm in spacing - on all
sides! This means hole diameter = diameter of heating pipe +
5/8/16 mm in expansion allowance. |
 |
11. Saw the panel
through the bored holes. When using a handsaw, remember:
always
saw
the panels from the upper side. Only place the pattern side
facing
downwards when using a
jigsaw or hand-held circular saw! |
 |
12. Apply glue to the
sawn-off piece and press tightly together behind the heating
pipe (using the pull-bar). |
 |
13. When a doorframe
has to be shortened: lay a panel next to the frame
(with the
pattern side
downward). Cut into the doorframe with a straight
back
saw, then slide panels under the frame
with pattern side
upwards. |
 |
14. Now were in the
home stretch! Measure the exact width of the last row.
To do
this lay a
panel on the previous row. Then lay a second panel on
the panel
to be measured with the
tongue to the wall and use a straight-edge. Dont forget
the wall spacing! Saw the panel
along
the marking. |
 |
15. Your installation
is almost finished! Fit the last panel carefully using the
pull-bar.
Allow 24 hours before you walk on the floor. |
|